City of Miami Dock Permit Rules
A City of Miami dock permit comes from the building department, under Chapter 29, Article III of the City Code. That article covers piers and docks alongside seawalls. The sections below are quoted word for word.
Why the article exists
The purpose of this article is to protect the public's health, welfare and safety by setting minimum standards to be used in the design, construction and maintenance of waterfront structures; further, to accomplish this purpose by requiring such design, construction and maintenance to be acceptable in all respects and particulars to the building and resilience and public works departments; and lastly, to ascertain that all physical improvements included herein are subject to and admit of rational analysis in accordance with established principles of mechanics and accepted engineering practices. This article shall be deemed to supplement the provisions of the South Florida Building Code.
Who signs off?
The building department. Nothing on the water gets built or repaired before that permit.
No waterfront improvement or structure shall be constructed, reconstructed or repaired until a permit authorizing such construction, reconstruction or repair has been obtained from the building department. No such permit shall be issued for any new construction or improvement or repair to an existing improvement or structure which is deemed, by the director of the building department to be substandard or not in compliance with the department of resilience and public works' design and construction standards.
Who answers for the design?
The engineer who prepares the plans. Docks are named in the list.
(a) Design analysis. Responsibility for proper design rests with the engineer who prepares the plans. Each improvement shall be designed to support all loads that may come upon it, to withstand the forces of water, wind and usage; and to meet the specific requirements of the building department and/or department of resilience and public works for location, elevation, and construction.
(1) General. Any improvement, bulkhead, seawall, pier, wharf, dock, groin, cut, marine, railway or other related structure included in this article shall admit of rational analysis in accordance with well-established principles of mechanics and sound engineering practices, and without exceeding the allowed stresses for the various materials as specified in the Florida Building Code.
What loads count
Thinking of a dock that carries a golf cart or a dock box full of gear? This is the list the engineer works from.
All improvements shall be proportioned for the following loads and forces:
(1) Dead load.
(2) Live load or surcharge including ordinary impact, except where loading involves unusual impact requiring increased assumed loads. Live loads may consist of material, goods or equipment stored or operated alongside the bulkhead, or any structure adjoining the same, the foundations of which may exert pressure on the bulkhead, or sidewalks, highway or street traffic loads. A sidewalk live load shall be taken as 100 pounds per square foot of sidewalk area, and the highway or street traffic loads shall be in accordance with the Standard Specifications for Highway Bridges adopted by the American Association of State Highway and Transportation Officials. Unless otherwise indicated by field conditions, the minimum highway or street traffic load shall consist of a two-axle truck of gross weight 20 tons, designated as class H-20 loading in such standard specifications.
(3) Impact and dynamic effect of live load.
Two more permits to expect
The county still needs its own DERM Class I permit for anything over tidal water. Zoning (Miami 21) also has dock rules. We haven't quoted those here, so ask the city's zoning office or your contractor.